The Barbican Centre, London |
| Type of Works | Area | Contract Period | | Installation of WP net system by rope access | 5,000m² | 6 Months | | Installation of safety lines by rope access | | | | Painting works by rope access | | |
http://www.barbican.org.uk/banqueting/private-hire/conservatory The challenge was to undertake a full roof maintenance programme consisting of repainting to the underside roof steelwork to the tropical gardens area without affecting day to day functioning of the conference centre; HASL worked in partnership with Vector Special Projects Ltd and installed a WP net system under slung with a visqueen membrane providing access for the painting team and created total exclusion of all works from the gardens below. This system was selected as no MEWP access was available, and proved to be a high cost effective, efficient method of working. ... ... ... |